Project Plan
As at 9 Oct 16
In Detail
18-19 Jan 16
Remove clock and clock face
8 Feb - 14 Mar 16
Building Phase I
- Rig Scaffolding
- Cut trap doors
- Re-position girders (level 3)
- Remove clock supports
- Replace roof girders
- Remove top section of chimney
Feb - 14 Mar 16
At bell foundry
- Cast new bells
14-31 Mar 16
- Remove bells and bell-frame
Apr-Jun 16
Building Phase II
- Footings for new frame
- Remove remainder of chimney
- Remove clock weights chute
- Create stone pads for frame supports
- Install frame foundations
Jun 16
At bell foundry
- Build new frame
Jul 16
- Renovate louvres
- Fit galebreaker
Aug 16
- Install new bell frame
- Rehang bells
- Replace clock room floor
- Finishing work and trials
- Remove scaffolding
- Close trap doors
End Aug 16
Replace clock
Fit handrail