Project Plan

As at 9 Oct 16

In Detail

18-19 Jan 16

Remove clock and clock face

 

8 Feb - 14 Mar 16

Building Phase I

  • Rig Scaffolding
  • Cut trap doors
  • Re-position girders (level 3)
  • Remove clock supports
  • Replace roof girders
  • Remove top section of chimney

 

Feb - 14 Mar 16

At bell foundry

  • Cast new bells

 

14-31 Mar 16

  • Remove bells and bell-frame

 

Apr-Jun 16

Building Phase II

  • Footings for new frame
  • Remove remainder of chimney
  • Remove clock weights chute
  • Create stone pads for frame supports
  • Install frame foundations

 

Jun 16

At bell foundry

  • Build new frame

Jul 16

  • Renovate louvres
  • Fit galebreaker

 

Aug 16

  • Install new bell frame
  • Rehang bells
  • Replace clock room floor
  • Finishing work and trials
  • Remove scaffolding
  • Close trap doors

 

End Aug 16

Replace clock

Fit handrail

A service of Re-dedication for the bells took place on Sunday 9 October 2016